Nordex has received new orders in France and Belgium covering the delivery and installation of 28 wind turbines across seven wind farms. Together, the projects represent 102 MW and each contract includes a multi-year service and maintenance agreement.
The customers and wind farm names have not been disclosed.
Turbine deliveries and installation work in the French regions of Pays de la Loire, Normandie, and Grand Est, and in the Ardennes and Wallonia in Belgium, are scheduled to begin in 2026 and 2027.
In France, one project will use five N131/3000 turbines. Two further projects will install eight and four N117/3675 turbines, while another will use four N149/4.X turbines, bringing the total to 77 MW. In Belgium, where orders total 25 MW, one project will receive three N131/3600 turbines and four N117/3675 turbines will be installed across two additional sites.